Main Site Master Plan and Elmwood Avenue

Front of lanyon building and front lawn in sunshine

Main Site Masterplan and Elmwood Avenue

Updated 14/12/2018.

 

Lanyon Building Conservation and Restoration Project

  • Brick and stonework repairs and restoration to the west elevation in Phase D (Great Hall and Main Entrance Tower).

Possible Impact: There will be some minor noise and disruption.

  • Window refurbishment and removals in Phase D (Great Hall and Main Entrance Tower).

Possible Impact: There will be some minor noise and disruption.

  • Contractor will be sealing windows internally to prevent dust ingress in Lanyon Building.

Possible Impact: Minor noise and disruption.

  • Phase D (Lanyon West/Main Entrance & Great Hall).

Possible Impact: The Great Hall will not be accessible until March 2019. There will be minor noise and disruption during the Phase D works. The main Contractor will be finalising the erection of scaffold and as a result there will be an increase in construction traffic. Construction plant will be accompanied by a banks-man. The Lanyon main entrance will be largely maintained throughout the works, however, there will be a number of occasions which will necessitate closure. Closures will be notified in advance and diversion signs installed.

  • Phase A (Lanyon South), Phase B (Lanyon South)

Possible Impact: The contractor will be completing snagging works to the brickwork and stonework, there may be minor noise and dust generated by these repairs.

  • Lawn adjacent to Lanyon North will be returfed next week.

Possible Impact: Minor noise and disruption

 

McClay Library Refurbishment Phase 3

  • Contractor's Compound.

Possible Impact: The attached drawing shows the location of the compound which will affect parking and access routes. 

  • Demolition, services installation and concrete cutting in David Bates Building.

Possible Impact: Noise from work in David Bates Building transferring to McClay Library. Some more intrusive and noisy work will take place after 6pm.

  • Construction works in courtyard between David Bates Building and McClay Library. 

Possible Impact: Noise from placing concrete and demolition work in courtyard.

  • Construction of concrete frame adjacent to Short Term Loans. 

Possible Impact: Noise transferring to Short Term Loans. 

 

Minor Projects

 

7-17 University Square

  • LEDS lighting to be fitted in some areas.

Possible Impact: Minor disruption.

 

2-8 Fitzwilliam Street Refurbishment

  • Refurbishment of 2-8 Fitzwilliam Street is underway with completion planned in February 2019.

Possible Impact: External decoration and erection of scaffolding to the façade.

 

 

Administration Building Level One

  • Refurbishment works to room within level one. 

Possible Impact: Area outside to be fenced off, no restrictions to walkways. 

 

Student Centre Enabling Works

  • Commencing of digging along Elmwood Mews and Elmwood Avenue for the Student Centre Enabling Works Service Diversions. It will complete at end of February.

Possible Impact: Parking restrictions along Elmwood Avenue and narrowing of footpaths for excavation.

  • Access to the Students Union building is currently restricted. Demolition and refurbishment survey will commence on Tuesday 11 Dece,ber 2018 and is programmed to be complete 21 December 2018.

Possible Impact: No access will be permitted to anyone other than the Contractor over this period. Should you have any concerns or issues, contact John Devlin, Estates Ext 1108.

  • Access to the former Students Union building is currently restricted. A demolition and refurbishment survey commenced on Tuesday 11 December 2018 and is programmed to be complete on 21 December 2018.

Possible Impact: No access will be permitted to anyone other than the Contractor over this period. Should you have any concerns or issues, contact John Devlin, Estates Ext 1108.