Main Site Master Plan and Elmwood Avenue

Front of lanyon building and front lawn in sunshine

Main Site Masterplan and Elmwood Avenue

Updated 18/04/2019.

 

 

Lanyon Building Conservation and Restoration Project

 

Phase D (Lanyon West/Main Entrance & Great Hall) 

  • There will be limited work on site over the coming week due to Easter holidays.

Possible Impact: There may be redecoration works within the Lanyon main entrance, with minimal impact on access.

 

McClay Library Refurbishment Phase 3 

  • Contractor's Compound.  

Possible Impact: The attached drawing shows the location of the compound which will affect parking and access routes.

  • Construction work at interface of David Bates Building and McClay Library.

Possible Impact: Noise transferring to McClay Library and David Bates Building. Some more intrusive and noisy work will take place before 10 a.m. and after 6 p.m.

  • Construction and roofing works in courtyard between David Bates Building and McClay Library.  

Possible Impact: Noise from demolition and building walls. There may be a background odour from roofing works. Intrusive and noisy work will take place before 10 a.m. and after 6 p.m.

  • Construction of external envelope and roofing adjacent to Short Term Loans.  

Possible Impact: Noise transferring to Short Term Loans. There may be a background odour from roofing works. Intrusive and noisy work will take place before 10 a.m. and after 6 p.m.

  • Construction works at McClay rear entrance.

Possible Impact: Low level noise. Noisier works will take place "out of hours".

  • Works in McClay Library Ground Floor.

Possible Impact: Corridor from the rear access door to Reception Desk is closed. Staff should use front entrance or temporary entrance at the bottom of staircase 3.

 

   

 

 

 

Minor Projects

 

Administration Building

  • Level One (Room 01 047) - refurbishment works.  Works are planned for completion in April 2019.  

Possible Impact: Low level noise.

  • Level One (Room 01 036) - internal refurbishment to provide new offices. Works are planned to commence early May 2019 with completion planned for end May 2019.

Possible Impact: Contractors compound will be located in the main site car park to the rear of the Administration Building. Car parking reduced by two spaces. Low level noise generated by the works. Pedestrian routes will be unaffected.

  • Levels Three and Four. Re-organisation work to happen over Easter and to be complete by week commencing 29 April 2019.

Possible Impact: No access to either floor while works are in progress.

 

South Dining Hall

  • Internal refurbishment of the South Dining Hall has commenced with completion planned for the end of April 2019.

Possible Impact: Contractors site compound will be located to the rear of the South Dining Hall. Reduced car parking to the rear of the South Dining Hall. Low level noise generated by the works. Pedestrian routes will be unaffected.