Campus Development: The Week Ahead
The Estates Directorate will do everything possible to manage the impact of works and we hope that they do not cause you too much inconvenience. If you have any comments regarding noise, please contact us on ext.5005 or email estates@qub.ac.uk.

Major Works projects, Minor Works projects and Campus Wide Building Condition Surveys will be taking place this week. Major Works projects include the new Seamus Heaney Centre, 4 University Street and Queen’s Media Lab. Minor Works projects include work at Lanyon and Physics, PEC, Geography and Administration Building. For more information, please see the drop-down menus below.
-
Major Projects
NEW SEAMUS HEANEY CENTRE (38 – 40 UNIVERSITY RD & 3 MOUNT CHARLES)
- Contractor’s compound located at the end of Mount Charles and adjacent to University Road. (Refer to attached drawing). Scaffolding in place on University Street.
Possible Impact: Restrictions to parking and pedestrian footpaths in place.
- Contractor deliveries to site.
Possible Impact: Site access is being manned by Contractor’s staff overseeing deliveries. Some disruption may be likely due to materials being delivered to site. Some noise and vibration from manoeuvring machines.
- Refurbishment works.
Possible Impact: Some noise and vibration from alterations to the existing structure/roof, installing partitions and fitting building services.
QUEEN’S MEDIA LAB – UNIVERSITY SQUARE
- Refurbishment of former garage on University Square Mews. Contractor’s compound area situated at University Square Mews site. Completion due at the end of June 2023.
Possible Impact: Potential for minor noise from roofing, site works and interior fit-out.
4 UNIVERSITY STREET
- Refurbishment of kitchens, bathrooms and electrical modifications within five apartments. Works are due for completion in early June 2023.
Possible Impact: Contractors’ compound within Mount Charles, minor dust, noise, vibration within occupied building. Shared access with Contractor due to single staircase building.
BUILDING CONDITION SURVEYS – CAMPUS WIDE
- A team of building surveyors are currently surveying every building space campus wide to establish future planned maintenance works. Building Liaison Officers will be contacted in advance by Jane Hartley, from Rider Levett Bucknall.
Possible Impact: Minimal impact but surveyors may need assistance in accessing rooms.
- Minor Works and Planned Maintenance
PEC SWIMMING POOL DRAINAGE
- Major new external drainage line being installed from swimming pool. Work is due to be completed by the end of June 2023.
Possible Impact: Increased activity in the area, dust, noise, vibration and plant moving. No staff or student access to affected areas.
GEOGRAPHY BUILDING – SECOND & THIRD FLOOR TOILET REFURBISHMENTS
- Refurbishment of male toilets on second floor and female toilets on third floor. Work is due for completion end of June 2023.
Possible Impact: Noise from power tools, hammers etc.
PEC - ROOM 0G 068
- Conversion of Squash Court 6 (Room 0G 068) to a group training suite. Work is due to be completed by the end of June 2023.
Possible Impact: Increased activity, dust, noise, vibration, personnel movement and delivery of materials.
NEW PHYSICS BUILDING – NANO LAB WORKSPACE, FIRST FLOOR
- Refurbishment of the entire open plan office area on the first floor. Will include removal of ceilings, data, lighting, carpet tiles and formation of new rooms. Work is due for completion in early September 2023.
Possible Impact: Noise from power tools, hammers etc.
PHYSICS - EMELEUS LECTURE THEATRE
- Upgrade of Audio Visual (A/V) system. Work is due to be completed by the end of June 2023.
Possible Impact: Increased activity, noise, personnel movement and delivery of materials. The Lecture Theatre will be closed off while works are ongoing.
PHYSICS - BELL LECTURE THEATRE
- Upgrade of Audio Visual (A/V system. Work is due to be completed by the end of June 2023.
Possible Impact: Increased activity, noise, personnel movement and delivery of materials. The Lecture Theatre will be closed off while works are ongoing.
LANYON – LECTURE THEATRE 01.052
- Upgrade of Audio Visual (A/V system. Work is due to be completed by the end of June 2023.
Possible Impact: Increased activity, noise, personnel movement and delivery of materials. The Lecture Theatre will be closed off while works are ongoing.
BUILDING CONDITION SURVEYS – CAMPUS WIDE
- A team of building surveyors are currently surveying every building space campus wide to establish future planned maintenance works. Building Liaison Officers will be contacted in advance by Jane Hartley, from Rider Levett Bucknall.
Possible Impact: Minimal impact but surveyors may need assistance in accessing rooms.
ADMIN BUILDING - LEVEL 3 CONFERENCE ROOM
- Upgrade of Audio Visual (A/V) system. Work is due to be completed by the end of July 2023.
Possible Impact: Increased activity, noise, personnel movement and delivery of materials.

No Major Works projects will be taking place this week. Minor Works projects and Campus Wide Building Condition Surveys will be taking place this week. Minor Works projects include work at MBC. For more information, please see the drop-down menus below.
-
Major Projects
No Major Works are currently planned.
- Minor Works and Planned Maintenance
MBC HAMMERHEAD (LOWER GROUND FLOOR) - ReVana LAB REFURB
- Removal of existing light fixings, ceilings, provision of timber stud walls, benches etc. Work is due for completion by early June 2023.
Possible Impact: Noise from power tools, hammers etc.
BUILDING CONDITION SURVEYS – CAMPUS WIDE
- A team of building surveyors are currently surveying every building space campus wide to establish future planned maintenance works. Building Liaison Officers will be contacted in advance by Jane Hartley, from Rider Levett Bucknall.
Possible Impact: Minimal impact but surveyors may need assistance in accessing rooms.
MBC SOUTH LECTURE THEATRE
- Upgrade of Audio Visual (A/V) system. Work is due to be completed by the middle of June 2023.
Possible Impact: Increased activity, noise, personnel movement, and delivery of materials. The Lecture Theatre will be closed off while works are ongoing.
MBC NORTH LECTURE THEATRE
- Upgrade of Audio Visual (A/V) system. Work is due to be completed by the middle of June 2023.
Possible Impact: Increased activity, noise, personnel movement, and delivery of materials. The Lecture Theatre will be closed off while works are ongoing.

Major Works projects, Minor Works projects and Campus Wide Building Condition Surveys will be taking place this week. Major Works projects include Management School (Riddel Hall). Minor Works projects include work in the David Keir Building (DKB), School of Biological Sciences, Ashby Tower, NITC, Malone Rd, Elms Drive Reception (BT9) and Riddel Hall Gatelodge. For more information, please see the drop-down menus below.
-
Major Projects
MANAGEMENT SCHOOL, RIDDEL HALL
The works to the new building are now complete.
- General snagging works.
Possible Impact: Some noise and vibration from pneumatic tools and hammers.
- Installation of the interactive e-learning suite.
Possible Impact: Some noise and vibration from pneumatic tools and hammers.
- Minor Works and Planned Maintenance
DKB SERVICE DUCT ACCESS HATCHES
- Work progresses on the installation of additional access hatches to the service ducts above the corridors. Work should be completed by the end of June 2023.
Possible Impact: Increased activity in the area, dust, noise, vibration and pedestrian diversions.
6 MALONE ROAD - CAR PARKING CONTROL
- Installation of retractable bollards to control access to parking. Work is due to be completed by the end of June 2023.
Possible Impact: Restricted parking. Some noise and vibration from groundwork and manoeuvring vehicles.
SCHOOL OF BIOLOGICAL SCIENCES – EXPANSION OF MASS SPECTROMETER ROOM
- New mass spectrometer service stations to be installed. Work is due to be completed by the end of June 2023.
Possible Impact: Some noise and possible dust.
ASHBY TOWER – REFURBISHMENT WORKS
- Refurbishment of rooms GM.002 and 11.002. Work is due for completion by the middle of June 2023.
Possible Impact: Increased activity, dust, noise, vibration, personnel movement, and delivery of materials in both areas.
ASHBY TOWER – LEVELS 7 & 8 DOOR ACCESS WORKS
- Door access to be installed on access points to Levels 7 and 8. Work is due for completion by the middle of June 2023.
Possible Impact: Increased activity, dust, noise, vibration, personnel movement and delivery of materials in both areas.
BT9 ELMS DRIVE RECEPTION, GROUND FLOOR
- Reconfiguration of the ground floor reception area. Work is due to be completed by the middle of June 2023.
Possible Impact: Increased activity, dust, noise, vibration, personnel movement, and delivery of materials. As the site is occupied, segregation will be put in place around the areas of work to safeguard staff and visitors.
NORTHERN IRELAND TECHNOLOGY CENTRE (NITC), CLOREEN PARK - SECOND FLOOR DIGITAL ROOM
- Works to form new wall, mount brackets etc. Work is due to be completed in late June 2023.
Possible Impact: Noise from power tools.
BUILDING CONDITION SURVEYS – CAMPUS WIDE
- A team of building surveyors are currently surveying every building space campus wide to establish future planned maintenance works. Building Liaison Officers will be contacted in advance by Jane Hartley, from Rider Levett Bucknall.
Possible Impact: Minimal impact but surveyors may need assistance in accessing rooms.
ASHBY TOWER - LECTURE THEATRE PHASE ONE
- Upgrade of Audio Visual (A/V) system. Work is due to be completed by the middle of June 2023.
Possible Impact: Increased activity, noise, personnel movement, and delivery of materials. The Lecture Theatre will be closed off while works are ongoing.
RIDELL HALL GATELODGE
- Internal refurbishment including kitchen and bathroom replacements. Work is due to be completed by the middle of August 2023.
Possible Impact: Increased activity, personnel movement and delivery of materials to site which will impact the front entrances.